Development of the Vöhringen Environmental and Energy Park
Municipalities
The municipality of Gingen an der Fils planned the extension of Austrasse in the section between Friedrichstrasse and Lindenstrasse. The planned measure included the replacement of the combined sewer for approx. 300 m, the replacement of the existing water pipe for approx. 300 m as well as the full extension of the roadway with approx. 2,100 m².
Consulting
Planning LPH 1 – 4
Planning LPH 5 – 7
Site Management / Local Construction Supervision
Earthworks: approx. 4,500 m³
Replacement combined sewer DN600 StB – approx. 300 m
Water pipe NW100 PE100 – approx. 300 m
Bituminous cover and base layers: approx. 2,100 m²